1 | | | Software Initiatives |
| | | | | 303d | 07/01/23 | 09/02/24 | 49% | | |
2 | | | Matt's Priorities |
| | | | | 303d | 07/01/23 | 09/02/24 | 30% | | |
3 | | | Core Technology Jira Dashboard |
| 2 | IT | Matt Edenhofer, zack.white@amerisbank.com | Shyam Kandavalli | TBD | TBD | TBD | 0% | Planned | BBDEV-19 |
4 | | | CC Encryption/Decryption (USA ePay aka Clover ---> SnapPay API) |
| 2 | IT | Matt Edenhofer | Shyam Kandavalli | 238d | 10/02/23 | 09/02/24 | 50% | In Progress | BBDEV-20 |
5 | | 2 | IT | Matt Edenhofer | Pat Byrne | TBD | TBD | TBD | 0% | Planned | BBDEV-58 |
6 | | | UAT Dev environment setup |
| 2 | IT | Matt Edenhofer | Matt Edenhofer | TBD | TBD | TBD | 0% | Planned | |
7 | | | 2024 Strategy |
| | | | | 207d | 07/01/23 | 04/19/24 | 8% | | |
13 | | | Melinda's Priorities |
| | | | | 28d | 04/08/24 | 05/15/24 | 47% | | |
14 | | 2 | Accounting | Fahim Khemji, Melinda de Leon | Jacquie | 28d | 04/08/24 | 05/15/24 | 50% | In Progress | mtg 5/13 |
15 | | | Status change in Vendor Manager |
| 2 | BC | Melinda de Leon, Truong Pham | Cheryl | 2d | 05/03/24 | 05/06/24 | 0% | In Progress | mtg 5/2 |
16 | | | Payoff & Close Order screen - Apply new calc to RB payoffs |
| 2 | Collections | Melinda de Leon, Shey Keith | Cesar | TBD | TBD | TBD | 0% | Planned | need tech specs |
17 | | | Payoff & Close Order screen - Apply new calc to TAMCO/BUSH payoffs |
| 2 | Collections | Melinda de Leon, Shey Keith | Cesar | TBD | TBD | TBD | 0% | Planned | need tech specs |
18 | | | Payoff & Close Order screen - Apply new calc to OP payoffs |
| 2 | Collections | Melinda de Leon, Shey Keith | Cesar | TBD | TBD | TBD | 0% | Planned | need tech specs |
19 | | | Payoff & Close Order screen - Booking Queue |
| 2 | Accounting | Melinda de Leon, Shey Keith | Jacquie | TBD | TBD | TBD | 0% | On Hold | on hold per Jacquie |
20 | | | Shey's Priorities |
| | | | | 92d | 01/02/24 | 05/08/24 | 58% | | |
21 | | | Payoff & Close Order screen - Apply new calc to CV payoffs |
| 2 | Collections | Shey Keith | Cesar | 5d | 05/02/24 | 05/08/24 | 0% | In Progress | Rollout 5/14 |
22 | | | Asset Management group and a Payoffs group - Add the user then adjust the automated assigned to this new user (BBAPP-3008) |
| 2 | CS | Shey Keith | Jeanette | 4h | TBD | TBD | 0% | Planned | BBDEV-31 |
23 | | | Identify all ways permissions are being set to be controlled by single page (PM) |
| 2 | IT | David Sherman, Shey Keith | Fahim Khemji | 89d | 01/02/24 | 05/03/24 | 70% | In Progress | BBDEV-32 |
24 | | | Change "Accounting" references to "Loan Ops" in PM, etc. |
| 2 | Accounting | Shey Keith | Jacquie | 2d | TBD | TBD | 0% | Planned | |
25 | | | Payoff Calc getting error message - BBAPP-2945 |
| 2 | CS | Shey Keith | Cesar | TBD | TBD | TBD | 0% | Planned | need scope |
26 | | | Autobook - Change the default value to use the most used default |
| 2 | Accounting | Shey Keith | Shey Keith | 1d | TBD | TBD | 0% | Planned | |
27 | | | Autobook - Remove View and replace with tables and joins to fix the timeout issue Accounting keeps getting |
| 2 | Accounting | Shey Keith | Shey Keith | 1d | TBD | TBD | 0% | Planned | |
28 | | | Invoice Screen in Collections - layout |
| 2 | Accounting | Shey Keith | MVV | 4h | TBD | TBD | 0% | Planned | |
29 | | | Collections - Fix Doc Request screen so if a company name has bad URL character - it replaces with _ character |
| 2 | Collections | Shey Keith | Shey Keith | 1d | TBD | TBD | 0% | Planned | |
30 | | | Performance Tuning - PM (research, test and learn) |
| 2 | IT | Shey Keith | Matt Edenhofer | 2d | TBD | TBD | 0% | Planned | |
31 | | | Modifying the collections screen and cleaning up data in the backend |
| 2 | Collections | Shey Keith | Jesus | 5d | TBD | TBD | 0% | Planned | |
32 | | | Improve the user experience once the invoices have been loaded into PM |
| 2 | Accounting | Shey Keith | MVV | | | | 0% | Planned | |
33 | | | Invoicing - create a duplicate “First Inv” module |
| 2 | Accounting | Shey Keith | MVV | 4h | TBD | TBD | 0% | Planned | |
34 | | | Ali's Priorities |
| | | | | 22d | 04/25/24 | 05/24/24 | 20% | | |
35 | | 2 | IT | Ali Zaiter | Phil Silva | 22d | 04/25/24 | 05/24/24 | 20% | In Progress | ETA 5/24 |
36 | | 2 | Collections | Ali Zaiter | Kris | TBD | TBD | TBD | 0% | Planned | BBDEV-48 |
37 | | | Vijay's Priorities |
| | | | | 25d | 04/08/24 | 05/10/24 | 75% | | |
38 | | | SOX App Integration with Boomi - Encompass |
| 2 | IT | Vijay Gaddam | zack.white@amerisbank.com | 25d | 04/08/24 | 05/10/24 | 75% | In Progress | |
39 | | 2 | IT | Vijay Gaddam | Matt Edenhofer | TBD | TBD | TBD | 0% | Planned | BBDEV-47 |
40 | | | Mohamed's Priorities |
| | | | | 112d | 11/29/23 | 05/03/24 | 56% | | |
41 | | | Ensure all CUBE reports include implicit yields (Phil's favorites) |
| 2 | Exec | Mohamed Deaghedy | Phil Silva | 50d | 02/26/24 | 05/03/24 | 75% | In Progress | sec dep report, maturity report. stacked ranking |
42 | | | CUBE Report cleanups w/ Kevin Umeda - Phase 1 |
| 2 | Exec | Mohamed Deaghedy | Phil Silva | 112d | 11/29/23 | 05/03/24 | 50% | In Progress | Need "Primary" items completed |
43 | | | Requirements_Transmittal Verbiage for Waived ACH Requirement v1.1 |
| 2 | BC | Mohamed Deaghedy | Vanessa | TBD | TBD | TBD | 0% | Planned | BBDEV-49 |
44 | | | Create DR version for JAX (EUS-133082/SYSENGSM-16039) |
| 2 | IT | Wei/Bob | Matt Edenhofer | 1w | TBD | TBD | 0% | Planned | Awaiting ETA |
45 | | | Fahim's Priorities |
| | | | | 21d | 04/15/24 | 05/13/24 | 63% | | |
46 | | | Financial Partners Aesthetics Rates - 2% for House (hidden rates, manual spreadsheets) |
| 2 | Sales | Fahim Khemji | Phil Silva | 15d | 04/15/24 | 05/03/24 | 85% | In Progress | Rollout 5/7 |
47 | | | Portal 360 system enhancements |
| 2 | Sales | Fahim Khemji | Carla | 9d | 05/01/24 | 05/13/24 | 25% | In Progress | Rollout 5/14 |
48 | | | Truong's Priorities |
| | | | | 6d | 04/26/24 | 05/03/24 | 75% | | |
49 | | | Create new email welcome notification for Vartana customers |
| 2 | BC | Truong Pham | Sophia Fields | 6d | 04/26/24 | 05/03/24 | 75% | In Progress | Rollout 5/7 |
50 | | | David's Priorities |
| | | | | 76d | 01/25/24 | 05/09/24 | 35% | | |
51 | | | Summary spreadsheet project |
| 2 | Accounting | David Sherman | Jacquie | 6d | 05/01/24 | 05/08/24 | 10% | In Progress | Rollout 5/9 |
52 | | | CUBE Report Clean Ups |
| | | | | 10d | 04/26/24 | 05/09/24 | 30% | | |
53 | | | CUBE report clean up - Place Vendor ID after every Vendor or Broker listing on all reports |
| 2 | Sales | David Sherman | Phil Silva | 5d | 04/26/24 | 05/02/24 | 90% | In Progress | |
54 | | | CUBE report clean up - Add date fields on all reports |
| 2 | Sales | David Sherman | Phil Silva | 5d | 05/03/24 | 05/09/24 | 0% | In Progress | |
55 | | | CUBE report clean up - Date of Hire on all Salesperson related reports |
| 2 | Sales | David Sherman | Phil Silva | 5d | 05/03/24 | 05/09/24 | 0% | In Progress | |
56 | | | CUBE report clean up - Segregate Originations and GM-based salespeople |
| 2 | Sales | David Sherman | Phil Silva | TBD | TBD | TBD | 0% | Planned | need scope |
57 | | | CUBE report clean up - Provide Toggle Switch for Current & Departed Reps and Current defaulting to Current |
| 2 | Sales | David Sherman | Phil Silva | TBD | TBD | TBD | 0% | Planned | need scope |
58 | | | CUBE report clean up - Make all formatting consistent |
| 2 | Sales | David Sherman | Phil Silva | TBD | TBD | TBD | 0% | Planned | need scope |
59 | | | CUBE report clean up - Verify Call Averages and Quotas are correct |
| 2 | Sales | David Sherman | Phil Silva | TBD | TBD | TBD | 0% | Planned | need scope |
60 | | | CUBE report clean up - refer to “GM by Opp” & “Originations by Opp,” not just GM or Originations |
| 2 | Sales | David Sherman | Phil Silva | TBD | TBD | TBD | 0% | Planned | Hold per Mohamed |
61 | | | Customer Registration (P360) with existing email |
| 2 | IT | David Sherman | Fahim Khemji | 5d | 01/25/24 | 01/31/24 | 75% | On Hold | w/ Tanveer - Jeanette feedback |
62 | | | Vendor Logo Setup Document - put the values in a config table and have the stored procedure read them |
| 3 | IT | David Sherman | David Sherman | TBD | TBD | TBD | 0% | Planned | need scope |
63 | | | Daniel/Mo's Priorities |
| | | | | 44d | 03/05/24 | 05/03/24 | 54% | | |
64 | | | Working on modernizing w/ Angular - Contract Mgr to AWS |
| | | | | 44d | 03/05/24 | 05/03/24 | 54% | | |
65 | | | Define API's needed/model updates |
| 2 | IT | Daniel Stark | Matt Edenhofer | 39d | 03/05/24 | 04/26/24 | 90% | In Progress | need to test API's |
66 | | 2 | IT | Daniel Stark | Matt Edenhofer | 27d | 03/21/24 | 04/26/24 | 50% | In Progress | Mo has completed what Truong has provided |
67 | | 2 | IT | Daniel Stark | zack.white@amerisbank.com | 35d | 03/18/24 | 05/03/24 | 50% | On Hold | Securing API keys, need to send to ARC (3/20) |
68 | | | Implement SSO with Azure Active Directory |
| 2 | IT | Daniel Stark | Matt Edenhofer | 30d | 03/25/24 | 05/03/24 | 50% | On Hold | |
69 | | | Send updates via e-mail anytime Contract Manager is updated (Franchesca) |
| 2 | IT | Daniel Stark | Matt Edenhofer | 6d | TBD | TBD | 0% | Planned | |
70 | | | Add admin page for user admin |
| 2 | IT | Daniel Stark | Matt Edenhofer | 6d | TBD | TBD | 0% | Planned | |
71 | | 2 | IT | Daniel Stark | Matt Edenhofer | 6d | TBD | TBD | 0% | Planned | |
72 | | 2 | IT | Daniel Stark | Matt Edenhofer | TBD | TBD | TBD | 0% | Planned | need scope |
73 | | | Convert CSSSP portal (HUB) to AWS |
| 2 | IT | Daniel Stark | Matt Edenhofer | TBD | TBD | TBD | 0% | Planned | need scope |
74 | | | Clinton's Priorities |
| | | | | 1d | 04/30/24 | 04/30/24 | 19% | | |
75 | | | Mirror the Originations Progress Report with Direct Sales Progress report |
| 2 | Sales | Clinton Brand | Kevin U | 1d | 04/30/24 | 04/30/24 | 95% | In Progress | Carla reviewing |
76 | | | Add profitability tab on Legal Metrics Report |
| 2 | Exec | Clinton Brand | Pat Byrne | 1d | TBD | TBD | 0% | On Hold | Jacquie to provide specs |
77 | | | Prefund Report - Add EC as a tab |
| 2 | Collections | Clinton Brand | Jim | 1h | TBD | TBD | 0% | Planned | |
78 | | | Convert Accounting Titled Vehicle Report to SSRS |
| 2 | Accounting | Clinton Brand | Jeanette | 3d | TBD | TBD | 0% | Planned | |
79 | | | Lidiya's Priorities |
| | | | | 47d | 03/01/24 | 05/06/24 | 84% | | |
80 | | | Cleanup Logins on Balboa SQL Instances (7 steps) |
| 2 | IT | Lidiya Tilahun | Matt Edenhofer | 45d | 03/01/24 | 05/02/24 | 90% | In Progress | sent to Matt for review |
81 | | | % of Deals Decisioned within 1 hour and 2 hours (SQL job) |
| 2 | IT | Lidiya Tilahun | Matt Edenhofer | 13d | 04/16/24 | 05/02/24 | 90% | In Progress | sent to Heather for review |
82 | | | Query optimization (latency) - cashed and uncashed read requests - Queries 341-360 |
| 2 | IT | Lidiya Tilahun | Shyam Kandavalli | 5d | 04/30/24 | 05/06/24 | 20% | In Progress | |
83 | | | Randy's/Edward's Priorities |
| | | | | 56d | 11/01/23 | 01/19/24 | 99% | | |
84 | | | In Queue |
| | | | | 56d | 11/01/23 | 01/19/24 | 99% | | |
87 | | | Salesforce Key Initiatives |
| | | | | | | | 0% | | |
88 | | | Tanveer's Priorities |
| | | | | | | | 0% | | |
89 | | 2 | IT | Tanveer | Matt Edenhofer | 4m | TBD | TBD | 0% | Planned | Need separate environment |
90 | | | | | | | | | | | |
91 | | | Strategic Initiatives |
| | | | | | | | 0% | | |
104 | | | | | | | | | | | |
105 | | | Completed |
| | | | | 1995d | 09/05/16 | 05/02/24 | 100% | | |
106 | | | 2016 |
| | | | | 84d | 09/05/16 | 12/29/16 | 100% | | |
122 | | | 2017 |
| | | | | 744d | 09/14/16 | 07/22/19 | 100% | | |
424 | | | 2018 |
| | | | | 556d | 11/21/16 | 01/07/19 | 100% | | |
821 | | | 2019 |
| | | | | 659d | 06/25/18 | 12/31/20 | 100% | | |
1064 | | | 2020 |
| | | | | 651d | 06/24/19 | 12/20/21 | 100% | | |
1638 | | | 2021 |
| | | | | 343d | 09/09/20 | 12/31/21 | 100% | | |
2182 | | | 2022 |
| | | | | 292d | 11/15/21 | 12/27/22 | 100% | | |
2660 | | | 2023 |
| | | | | 321d | 10/03/22 | 12/29/23 | 100% | | |
3300 | | | 2024 |
| | | | | 642d | 11/11/21 | 05/02/24 | 100% | | |
3508 | | | | | | | | | | | |