Hyde-Addison Renovation & DCPS Timeline and Background
On March 11, 2016 DC Public Schools (DCPS) blindsided the Hyde-Addison Community with new delays and unacceptable recommendations for the long overdue renovation of Hyde-Addison Elementary School.
The most recent expectations of the local community for this necessary renovation project, which has been consistently delayed since 2012, had been for a single year of construction throughout the 2016-17 school year during which students could remain in the school. However, in December 2015, DCPS notified the Hyde-Addison community that students would need to relocate after all and a relocation swing space would be necessary for up to two years. This was the first blindside for parents who had previously been assured their children would not need to relocate and that the project would impact only a single school year.
Given the unexpected news that a swing space would be necessary, the Hyde-Addison School Improvement Team, in conjunction with parents, strongly stated to DCPS the preference for the vacant, local, and DCPS-owned Duke Ellington School of Arts (DESA) field.
Nonetheless, on March 11, DCPS blindsided the Hyde-Addison community a second time by stating that no acceptable local swing space could be found for 2016-17 and thus the project is delayed yet again while an acceptable swing space is sought. DCPS did not provide compelling reasons, but mentioned the opposition of Burleith residents, who put forward various non-compelling arguments for why the vacant and DCPS-owned property should remain empty and not be used as a temporary location for its neighbor community elementary school students. At the same time and in complete disregard of Hyde families’ request for a local swing space, DCPS also issued its recommendation for the swing space, starting in August 2017, to be Meyer Elementary School, on 11th Street far across town and through the worst of DC traffic. Additionally Meyer Elementary School is currently used by DESA students while their $250 million renovation occurs, which thus eliminates this option as a valid option in 2017 should that mammoth undertaking fall behind schedule.
Needless to say, the Hyde-Addison community finds this new delay and the DCPS swing space recommendation unacceptable. We strongly ask your support in adding your name to this petition.